Local Plan timetable

The council published the Local Plan timetable on 9 October 2026 and the timetable has effect from that date.

The timetable shows the milestones required to meet the government’s 30-month local plan process. Throughout the process the timetable will be kept under review monthly and updated when necessary and the effect date will be amended to reflect changes.

The timetable is available to view at the Civic Offices in London Road, Basingstoke, from 8.30am to 4.30pm Monday to Friday. It is also available at libraries during their opening hours (Basingstoke Discovery Centre, Chineham Library, Mortimer Library, Newbury Library, Overton Library, Tadley Library and Whitchurch Library). Copies can be made available to members of the public on request.

The Local Plan timetable CSV file contains the timetable in machine readable format. The data meets the government's statutory data standards and is provided under the Open Government Licence.

Timetable

Local Plan Milestone Date
Publish notice of intention to commence 9 October 2026
Scoping consultation 9 October 2026 to 20 November 2026
Gateway 1 self-assessment 12 March 2027
Content and evidence consultation (Regulation 23) 2 July 2027 to 27 August 2027
Gateway 2 advise sought 10 January 2028
Proposed plan consultation (Regulation 27) 30 June 2028 to 25 August 2028
Gateway 3 advise sought 8 January 2029
Submission for examination 23 February 2029
Adopted 20 September 2029

Schedule of timetable amendments

No amendments have been made to the timetable to date.