Development delivering BNG will need to ensure certain statutory requirements are met, including:
- A minimum 10% BNG is achieved
- BNG is calculated using the latest version of the statutory biodiversity metric (or the ‘small sites metric’ for qualifying minor development)
- Adherence to the biodiversity gain hierarchy
- Secure, manage and monitor all offsite and significant onsite habitat enhancements for a minimum of 30 years
Development cannot commence until a Biodiversity Gain Plan (and relevant supporting information) is submitted to and approved by the local planning authority to discharge the pre-commencement condition.
Developers should refer to the planning practice guidance and government BNG statutory guidance for further detail on all statutory requirements.
Phased development
Specific BNG arrangements apply for development that is phased, to reflect the long-term timeframe. This includes an alternative approach to Biodiversity Gain Plans (BGP), where the outline permission will require the submission and approval of an Outline BGP, and subsequent reserved matters for each phase will require the submission and approval of a Phase BGP before commencement. Please refer to government guidance for further information.
Biodiversity gain hierarchy
In line with government guidance, developments must ensure they prioritise the delivery of BNG onsite first, and where it is not possible to deliver all of it onsite, then to secure offsite BNG. Where this is not possible, developers can purchase ‘statutory credits’ from the government as a last resort. These steps can be combined but must be followed in order.
It should be noted that the biodiversity gain hierarchy is distinct from the general mitigation hierarchy outlined in national policy, which should be considered as a first rule regarding the protection of biodiversity, i.e. avoid impacts in the first instance, where this is not possible mitigate those impacts, and as a last resort, compensate those impacts.
Small sites
Small sites (i.e. ‘minor’ development) may use the simpler ‘small sites metric’ provided no onsite priority habitat is being impacted and all BNG will be delivered onsite. For cases intending to deliver or secure offsite BNG, the full statutory metric should be used.
The biodiversity gain hierarchy is relaxed for small sites which means they can seek offsite BNG in the first instance if they wish.
Securing significant onsite BNG
The council has an established approach that any onsite BNG deemed as ‘significant’ must be legally secured via S106 agreement with the council as a long term and robust mechanism to ensure its implementation, management and monitoring over 30 years.
What constitutes significant onsite enhancements will be determined by the council on a case-by-case basis, but examples may include the creation of a wildflower meadow, a nature park, or a stretch of species-rich native hedgerow. A rough guide to what the council is likely to consider as ‘significant’ onsite enhancements includes:
- habitats of medium or higher distinctiveness
- habitats of low distinctiveness which create a large number of biodiversity units
- areas of habitat creation or enhancement which are significant in area relative to the size of the development
Significant onsite BNG will need to be delivered and monitored in line with a Habitat Management and Monitoring Plan, to be submitted and approved as part of the discharge of the biodiversity gain condition.
Habitat enhancements that are considered ‘non-significant’ may still require a planning condition to secure their implementation and management as considered necessary by the council.
Securing offsite BNG
All offsite BNG (i.e. BNG delivered on land outside of the red line boundary) must be secured by a legal agreement, either via a S106 with the council, or a conservation covenant with a Responsible Body. Developers can achieve this via one of the following ways:
- Developer-led offsite BNG on their own land – in this case the developer also acts as landowner. The following steps would need to be followed prior to submission of the Biodiversity Gain Plan to discharge the biodiversity gain condition:
- Obtain a legal agreement to secure the implementation, management and monitoring of the offsite BNG
- Obtain an approved Habitat Management and monitoring Plan (HMMP) and finalised metric (from the council in the case of a S106 agreement)
- Apply to register the site on the national Biodiversity Gain Site Register, ensuring submission of all required documentation (including plans, the legal agreement, full metric, HMMP, and a local land charge search certificate)
- Once registered, record the allocation of units to the development and obtain the necessary reference number from the Register to inform the Biodiversity Gain Plan.
Currently the council ensures the above steps are covered as obligations within the legal agreement issued alongside planning consent. The developer should ensure they factor in the time needed to complete these steps prior to development commencing. Please see government guidance for further advice for land managers.
- Purchase biodiversity units from the offsite BNG market – biodiversity units allocated under an established habitat bank scheme are already covered by the habitat bank’s own legal agreement and HMMP. The developer would need to have the allocation recorded to their development on the national Biodiversity Gain Site Register and provide evidence of this along with a fully completed statutory metric, to support its Biodiversity Gain Plan when applying to discharge the general gain condition before development commences.
Further information can be found here: Make off-site biodiversity gains as a developer - GOV.UK
Strategic significance
Strategic significance is the local significance of a habitat based on its location and habitat type. In Hampshire, the Hampshire Local Nature Recovery Strategy should be used to determine strategic significance. It can be applied in the metric for proposed habitats that fall within the Local Habitat Map and align with identified potential measures for that habitat parcel. This provides an enhanced ‘score’ so that more biodiversity units are generated (a 15% uplift), to incentivise developers to target BNG in mapped LNRS areas.
Please refer to the Statutory Metric User Guidance for further information.